Birds Eye Case Study
31 Jan
Birds Eye

COMPANY:
Birds Eye

LOCATION:
Lowestoft

OVERVIEW:
Enclosure to avoid
contamination of adjacent
production areas, whilst
building works are in
progress

SOLUTION:
Flexiscreen®

What did the client say?

“Having worked with Westgate previously, it was no surprise that their Flexiscreen dust screen and expertise were ideal for our requirements. The screen did exactly what we needed it to do and offered us robust protection against contamination control during refurbishment works.”

For over 60 years, Birds Eye have been offering a vast range of quality frozen food products that make it easier for people to prepare simple but healthy meals at home.

Westgate have developed a great working relationship with this renowned and highly recognised brand, delivering multiple partitioning projects over the years.

Birds Eye
Birds Eye
Birds Eye

In this most recent project, Birds Eye were tasked with carrying out some works to an existing process area at their factory in Lowestoft. This involved removing some existing masonry walls and installing new walls and doors. All of this needed to be achieved without contaminating the existing process plant.

Due to the strong relationship with Birds Eye, Westgate were asked to facilitate a solution. Flexiscreen was recommended for a number of reasons, with the first of those being specific to this project: Flexiscreen can be easily installed at an angle, which is a very big advantage over conventional temporary screening methods. This meant that the final screen could be hung from the ceiling and then slope out by 1.5 meters before being battened to the floor, enabling Birds Eye to screen off the exact area requiring the works, without taking up lots of existing floor space.

Flexiscreen’s ability to fit seamlessly floor to ceiling without gaps and its panels that connect using a V-overlap system (creating an over 99% dust tight seal) added to the reasons that Flexiscreen was the ideal screening solution for this project and building works within the food manufacturing sector.

One of the other main benefits of Flexiscreen is that a bespoke design can be profiled and then manufactured off-site for a quick and clean onsite installation: this reduces downtime onsite which is also very valuable to food manufacturers and also comes in a range of colours and materials dependant on the project/client needs.

A zip access doorway was incorporated to enable access into the work area for plant and equipment, without compromising on the dust tight seal. Westgate installed the main project and then returned to the site to remove the end elevation and extend the screen to incorporate another area. This was easily achieved because Flexiscreen can be efficiently installed, adapted and removed without lasting damage to the premises. Quote to installation took 4 weeks and the full installation took just 3 days. Learn more about Flexiscreen®